CASE STUDY: The Crick L08 Skylab, London

Work to be undertaken: We have acted as QS from inception to agreement of the final account for The Crick have built a 900sq.m, multimillion Skylab at Level 8 & 9 which is a new technical research hub with Cat 2 Labs, associated write up space and meeting room.

Benefits to our client: As the project started 50m above ground level and was over a live research lab, the Crick require proactive cost planning, cost reports and we achieved the agreement of the final account before completion on site.

The Crick L08 Skylab
Neilcott Construction
Architon LLP
Completed July 2024